TIP PROCESS FLOW

Flow chart legend

PHASE 1: GETTING STARTED

  • Meet with the Airport District Manager to verify you have conceptual level approval prior to developing your design

Step 2: Initial Submission & Lease Verification

  • PMO reviews for 30% plan completion
    • You may bypass the 30% conceptual plans step if you are ready to submit 100% plans***
  • If approved, PMO forwards to DOT-A Reviewers
  • If rejected, Tenant received comments to address for resubmission
  • Multi-section Engineering Branch review:
    • AIR-ED: Design Section
    • AIR-EP: Planning Section
    • AIR-ER: Program Management Office
    • AIR-EE: Environmental Section
      • AIR-EE will contact Tenant to setup Veoci account and submit information via Veoci
    • AIR-EC: Construction
    • AIR-EM: Facilities Maintenance
    • AIR-L: Operations
    • AIR-PM: Property Management
  • DOT-A Reviewers submit comments for Tenant to address
  • Following review, Tenant to receive compiled package of all review comments
Phase 1 tip process flow

PHASE 2: DESIGN APPROVAL

Step 5: Full Submission (100% Contract Documents)

  • 100% design drawings
  • Specifications
  • Environmental Compliance
  • Updated Construction Cost Estimate

Step 6: Review by PMO

  • PMO verifies that all required documents are submitted for a 100% submission
  • If approved, PMO forwards to relevant DOT-A Reviewers
  • If rejected, Tenant receives comments to address for resubmission

Step 7: Review by DOT-A

  • Comprehensive review by all Engineering Branch sections:
    • AIR-EC: Construction Section
    • AIR-ED: Design Section
    • AIR-EE: Environmental Section
    • AIR-EG: Drafting Section
    • AIR-EM: Facilities Management Section
    • AIR-EP: Planning
    • AIR-ER: Program Management Office
    • AIR-LF: Aircraft Rescue & Firefighting
  • If “Approved (As Noted)”, Tenant to address all comments prior to moving onto the pre-construction phase
  • If “Disapproved,” or “Revise and Resubmit,” Tenants are to address all comments and revise for resubmission
Tip process flow phase 2

PHASE 3: PRE-CONSTRUCTION

Step 8: Submit Necessary Forms

  • Certificate of Insurance (COI) Instructions: See Manual 1, Appendix, Form M. 1-2
  • Permit to Perform Work on State Airport Property: See Manual 1, Appendix, Form M. 1-5
  • Following permit issuance, submit Application for Interruption of Airport Services (Outage Request): See Manual 1, Appendix, Form M. 1-6
    • If the work may impact surrounding tenants, airport operations, or airport users, the tenant must complete the Outage Request form (See Resources page).
    • Requirements for outages are outlined in paragraphs 3.3.6 G – Utility Services and Charges and paragraph 3.5.5 – Schedule Utility Outage in the TIG Manual 1

    Step 9: Final Approval & Notice to Proceed

    Step 10: Pre-Construction Meeting & Mobilization

    • Pre-construction meeting schedules at least five (5) days prior to the start of construction
      • Attendees: Tenant / Contractor / Subcontractors / DOTA Inspector / PMO Inspector / Airport Operations / Security (as required)
      • Review: Approved plans, permit conditions (M. 1-5), construction schedule & phasing, safety plan, security, logistics plan, utility outage coordination (M. 1-6), airport access, badging, escorts, delivery routing, workforce, equipment, and staging area(s)
      • Deliverables: Pre-Construction Meeting Minutes and confirmation of badging and security compliance
    Tip process flow phase 3

    PHASE 4: CONSTRUCTION

    Step 11: Construction Execution & Quality Assurance

    • Contractor Responsibilities:
      • Build according to 100% approved plans and specs
      • Maintain QA program and on-site supervision
      • Required QA documentation
      • Daily reports & safety logs (weather, personnel, tasks, equipment, etc.)
      • Maintain site safety per airport requirements
      • Protect airport operations and public safety at all times
      • Compliance with TIG Manual 2 standards
      • Testing, inspection, and commissioning logs
      • RFIs, Submittals, & Change Requests
      • Weekly coordination meetings
    • Note: any changes from approved plans requires DOTA approval before execution***

    Step 12: Construction Inspections

    • Preparatory Meeting
    • Initial Inspection
      • Civil / architectural / MEP
      • Life-safety and fire protection (via ARFF and AIR-LF)
      • Environmental compliance (via AIR-EE)
      • Airport security compliance
      • Equipment and system testing
      • Deficiencies
    • Follow-Up Inspections
    • Note: non-compliant work will be documented***
      • Contractor to correct non-compliant work before next phase continues

    PHASE 5: COMPLETION / MOVING IN / ENFORCEMENT

    Step 13: Substantial Completion & Closeout

    • Required submittals:
      • As-Builts / Record Drawings
      • Punch list request
      • Final system testing results and commissioning reports
      • O&M Manuals and warranties
      • Final schedules and logs
      • Environmental clearance confirmations
      • Fire and life-safety acceptance documentation
      • FAA compliance documentation (if applicable)
      • DOTA actions
    • Joint punch-list walk-through
    • Issuance of Substantial Completion acknowledgement
    • Issuance of Certificate of Construction Completion (required for return of deposit)
    • Approval to remove temporary barriers and controls

    Step 14: Final Acceptance & Turnover

    • Final inspection and sign-off by DOTA
    • Tenant reviews Final Acceptance letter
    • Closeout package finalized:
      • Approved and stamped as-built drawings
      • Warranty list and services contacts
      • Final environmental sign-off
      • Security clearance and badge return
      • Utility metering updates (if applicable)
      • Contractor warranty
    • Tenant moves to operational status (space placed into active use)
    Tip process flow phase 5

    Need more information? Contact us.