TIP PROCESS FLOW

TIP process flow legend: orange equals tenant (you), blue equals PMO (Oceanit), and green equals DOT airports. Red rhombus equals decision. Oval indicates a start or end to a process.

PHASE 1: GETTING STARTED

  • Meet with the Airport District Manager to verify you have conceptual level approval prior to developing your design

Step 2: Initial Submission & Lease Verification

  • PMO reviews for 30% plan completion
    • You may bypass the 30% schematic plans step if you are ready to submit 100% plans***
  • If approved, PMO forwards to DOT-A Reviewers
  • If rejected, Tenant received comments to address for resubmission
  • Multi-section Engineering Branch review:
    • AIR-ED: Design Section
    • AIR-EP: Planning Section
    • AIR-ER: Program Management Office
    • AIR-EE: Environmental Section
      • AIR-EE will contact Tenant to setup Veoci account and submit information via Veoci
    • AIR-EC: Construction
    • AIR-EM: Facilities Maintenance
    • AIR-L: Operations
    • AIR-PM: Property Management
  • DOT-A Reviewers submit comments for Tenant to address
  • Following review, Tenant to receive compiled package of all review comments
Step 1: Preliminary meeting with the ADM flow chart
Step 2 through 4 of process flow chart

PHASE 2: DESIGN APPROVAL

Step 5: Full Submission (100% Contract Documents)

  • 100% design drawings
  • Specifications
  • Environmental Compliance
  • Updated Construction Cost Estimate

Step 6: Review by PMO

  • PMO verifies that all required documents are submitted for a 100% submission
  • If approved, PMO forwards to relevant DOT-A Reviewers
  • If rejected, Tenant receives comments to address for resubmission

Step 7: Review by DOT-A

  • Comprehensive review by all Engineering Branch sections:
    • AIR-EC: Construction Section
    • AIR-ED: Design Section
    • AIR-EE: Environmental Section
    • AIR-EG: Drafting Section
    • AIR-EM: Facilities Management Section
    • AIR-EP: Planning
    • AIR-ER: Program Management Office
    • AIR-LF: Aircraft Rescue & Firefighting
  • If “Approved (As Noted)”, Tenant to address all comments prior to moving onto the pre-construction phase
  • If “Disapproved,” or “Revise and Resubmit,” Tenants are to address all comments and revise for resubmission
Tip process flow phase 2

PHASE 3: PRE-CONSTRUCTION

Step 8: Submit Necessary Forms

  • Certificate of Insurance (COI) Instructions: See Manual 1, Appendix, Form M. 1-2
  • Permit to Perform Work on State Airport Property: See Manual 1, Appendix, Form M. 1-5
  • Following permit issuance, submit Application for Interruption of Airport Services (Outage Request): See Manual 1, Appendix, Form M. 1-6
    • If the work may impact surrounding tenants, airport operations, or airport users, the tenant must complete the Outage Request form (See Resources page).
    • Requirements for outages are outlined in paragraphs 3.3.6 G – Utility Services and Charges and paragraph 3.5.5 – Schedule Utility Outage in the TIG Manual 1

Step 9: Final Approval & Notice to Proceed

Step 10: Pre-Construction Meeting & Mobilization

  • Pre-construction meeting schedules at least five (5) days prior to the start of construction
    • Attendees: Tenant / Contractor / Subcontractors / DOTA Inspector / PMO Inspector / Airport Operations / Security (as required)
    • Review: Approved plans, permit conditions (M. 1-5), construction schedule & phasing, safety plan, security, logistics plan, utility outage coordination (M. 1-6), airport access, badging, escorts, delivery routing, workforce, equipment, and staging area(s)
    • Deliverables: Pre-Construction Meeting Minutes and confirmation of badging and security compliance
Phase 3 pre-construction process flow

PHASE 4: CONSTRUCTION

Step 11: Construction Execution & Quality Assurance

  • Contractor Responsibilities:
    • Build according to 100% approved plans and specs
    • Maintain QA program and on-site supervision
    • Required QA documentation
    • Daily reports & safety logs (weather, personnel, tasks, equipment, etc.)
    • Maintain site safety per airport requirements
    • Protect airport operations and public safety at all times
    • Compliance with TIG Manual 2 standards
    • Testing, inspection, and commissioning logs
    • RFIs, Submittals, & Change Requests
    • Weekly coordination meetings
  • Note: any changes from approved plans requires DOTA approval before execution***

Step 12: Construction Inspections

  • Preparatory Meeting
  • Initial Inspection
    • Civil / architectural / MEP
    • Life-safety and fire protection (via ARFF and AIR-LF)
    • Environmental compliance (via AIR-EE)
    • Airport security compliance
    • Equipment and system testing
    • Deficiencies
  • Follow-Up Inspections
  • Note: non-compliant work will be documented***
    • Contractor to correct non-compliant work before next phase continues

PHASE 5: COMPLETION / MOVING IN / ENFORCEMENT

Step 13: Substantial Completion & Closeout

  • Required submittals:
    • As-Builts / Record Drawings
    • Punch list request
    • Final system testing results and commissioning reports
    • O&M Manuals and warranties
    • Final schedules and logs
    • Environmental clearance confirmations
    • Fire and life-safety acceptance documentation
    • FAA compliance documentation (if applicable)
    • DOTA actions
  • Joint punch-list walk-through
  • Issuance of Substantial Completion acknowledgement
  • Issuance of Certificate of Construction Completion (required for return of deposit)
  • Approval to remove temporary barriers and controls

Step 14: Final Acceptance & Turnover

  • Final inspection and sign-off by DOTA
  • Tenant reviews Final Acceptance letter
  • Closeout package finalized:
    • Approved and stamped as-built drawings
    • Warranty list and services contacts
    • Final environmental sign-off
    • Security clearance and badge return
    • Utility metering updates (if applicable)
    • Contractor warranty
  • Tenant moves to operational status (space placed into active use)
Phase 5 completion process flow